SYSTEMA ING
First avis seen 2025-05-19
7
Awards won
6
Buyers served
1028508
Total won
96000
Median amount
57600
Smallest
452400
Largest
7.6
Average competitors
Built from results published under this exact name. An avis never names who might bid on it, so only the award side exists for a company.
Who they win from
Recent results
| Reference | Subject | Amount incl. tax | Quotes received | Published on |
|---|---|---|---|---|
19/2026 |
Etude de protection contre les inondations du souk de la commune saada | 96000 | 7 | 2026-08-31 |
27/2026 |
Etude de construction de la RP1918 du PK 7+790 au PK17+890 dans la province de Sidi Ifni. | 73932 | 7 | 2026-08-07 |
SA/18/2026 |
ETUDE DE CONSTRUCTION DE LA RP 2005 DU PK 27+100 ( ex PK 10+000) au PK 37+100 (ex PK 0+000 ) DANS LA PROVINCE DE YOUSSOUFIA -REGION MARRAKECH-SAFI | 73800 | 7 | 2026-07-14 |
15/2026 |
Étude de protection de la RN27 au PK 109 contre l'instabilité et l’érosion de la plate forme routière générées par l’effet de sapement de oued Rdoum et autres risques (prestation urgente et le BET doit être obligatoirement agréé) | 156000 | 9 | 2026-03-05 |
35/2025 |
ETUDE DE RECONSTRUCTION D’UN OUVRAGE HYDRAULIQUE AU PK 53+420 DE LA RR121 (PK 991 DE L’EX RN1) DANS LA PROVINCE DE SIDI IFNI. | 57600 | 11 | 2025-12-14 |
60/2025/DPETLOA |
: Programme Prioritaire de connectivité intercommunale 2025-2026 : Etude de construction des routes sur 26.2 Km dans les communes de Guenfouda, Sidi Boubker, Lamrija et Laaouinat sur dans la Province de Jerada | 118776 | 9 | 2025-12-13 |
09/AREPDT/2025 |
Programme National pour l'Approvisionnement en Eau Potable et d’Irrigation : Actualisation de l’étude de conception et suivi des travaux de construction du barrage Jouijel au niveau de la commune Sidi Ali – Province d’Errachidia | 452400 | 3 | 2025-05-19 |